Bellefonte Nuclear Generating Station

From Wikipedia, the free encyclopedia - View original article

Bellefonte Nuclear Generating Station
Bellefonte Nuclear Power Plant.jpg
Bellefonte Nuclear Generating Station is located in Alabama
Location of Bellefonte Nuclear Generating Station
CountryUnited States
LocationHollywood, Alabama
Coordinates34°42′31″N 85°55′45″W / 34.70861°N 85.92917°W / 34.70861; -85.92917Coordinates: 34°42′31″N 85°55′45″W / 34.70861°N 85.92917°W / 34.70861; -85.92917
StatusProposed
Construction costUS$6 billion (Units 1 & 2)
Owner(s)Tennessee Valley Authority
Reactor
Reactors planned2 x 1,100 MW[1]
Reactor type(s)Pressurized water reactor
Reactor supplier(s)Babcock and Wilcox[1]
 
Jump to: navigation, search
Bellefonte Nuclear Generating Station
Bellefonte Nuclear Power Plant.jpg
Bellefonte Nuclear Generating Station is located in Alabama
Location of Bellefonte Nuclear Generating Station
CountryUnited States
LocationHollywood, Alabama
Coordinates34°42′31″N 85°55′45″W / 34.70861°N 85.92917°W / 34.70861; -85.92917Coordinates: 34°42′31″N 85°55′45″W / 34.70861°N 85.92917°W / 34.70861; -85.92917
StatusProposed
Construction costUS$6 billion (Units 1 & 2)
Owner(s)Tennessee Valley Authority
Reactor
Reactors planned2 x 1,100 MW[1]
Reactor type(s)Pressurized water reactor
Reactor supplier(s)Babcock and Wilcox[1]

The Bellefonte Nuclear Generating Station (shortly BLN) is a partially completed nuclear power plant located in Hollywood, Alabama. A total of four reactors have been proposed over a period of 40 years, and billions of dollars have been spent, but no electricity has yet been produced. The site has sat idle for more than 20 years and some spare parts have been taken from the two incomplete units. In 2011, the Tennessee Valley Authority board of directors approved a plan to restart construction of the Bellefonte Unit 1 reactor.[2] But the ultimate cost and timing for Bellefonte 1 will depend on work at another reactor TVA is completing - Watts Bar 2 in Tennessee. In February 2012, TVA said the Watts Bar 2 project was running over budget and behind schedule.[3]

Units 1 and 2[edit]

The Bellefonte Nuclear Generating Station site is owned by the Tennessee Valley Authority and is located in Hollywood, Alabama. The two partially built 1,256 megawatt (MWe) pressurized water reactors on the site were made by Babcock and Wilcox and are called a 205 design due to the number of fuel assemblies in the core. These units are of the same design as WNP-1 which is also unfinished, and as the Mülheim-Kärlich A reactor in Germany that operated for three years and proved the design. Unit 1 was 88% complete and Unit 2 was 58% when development was suspended in 1988 after a $6 billion investment. Subsequent asset recovery activities, along with more recent inspections of remaining equipment, resulted in BLN 1&2 now being considered approximately 55 percent and 35 percent complete, respectively.[4]

Although the construction permits were terminated on September 15, 2006, TVA is investigating completion of these first two units with operation projected to start Unit 1 in 2017 and Unit 2 in 2021. In August 2008 TVA asked the NRC to reinstate the construction permits as part of the restart evaluation. This request was granted by the NRC on February 9, 2009, albeit as a terminated application which required significant inspection of all systems to bring the license to the deferred stage. The status was upgraded January 14, 2010 to deferred.[5]

Units 3 and 4[edit]

On September 22, 2005 it was announced that Bellefonte was also selected as the site for one or two AP1000 pressurized water reactors to be called Units 3 and 4. TVA filed the necessary applications[6] in November 2007 to begin the design and construction process. For details, see Nuclear Power 2010 Program.

In August 2009, the Tennessee Valley Authority, faced with "falling electric sales and rising costs from cleaning up a massive coal ash spill in Tennessee", trimmed plans for the potential four-unit Bellefonte nuclear plant to one reactor.[7]

Recent developments[edit]

On August 20, 2010 the TVA Board of Directors authorized $248 million to continue development of the Bellefonte Unit 1.[8] On August 18, 2011, the TVA board of directors voted to move forward with the construction of the unit one reactor at Bellefonte.[9]

But as of March 2012, many contractors have been laid off and the ultimate cost and timing for Bellefonte 1 will depend on work at another reactor TVA is completing - Watts Bar 2 in Tennessee. In December 2012, TVA said the Watts Bar 2 project is on schedule to finish in December 2015.[10]

TVA again announced staffing cuts at the plant in June 2013, reducing staffing at the plant from 540 to approximately 140.[11][12]

In October, 2013, it was announced that former TVA Chairman Dennis Bottorff and financier Franklin L. Haney have drafted a proposal to finish the Bellefonte Nuclear Plant using private funds and federal tax credits.[13]


Reactor data[edit]

The Bellefonte Generating Station consist of two cancelled reactors, two additional are planned.

Reactor unitReactor typeCapacityConstruction startedElectricity grid connectionCommercial operationShutdown
NetGross
Bellefonte-1[14]B&W-2051235 MW1263 MW01.01.1974Cancelled construction on 01.01.1988, but planned to resume construction
Bellefonte-2[15]B&W-2051235 MW1263 MW01.01.1974Cancelled construction on 01.01.1988
Bellefonte-3[16]AP10001117 MW0 MWCancelled plan
Bellefonte-4[17]AP10001117 MW0 MWCancelled plan

References[edit]

  1. ^ a b NRC: Bellefonte Nuclear Site, Units 3 and 4 Application
  2. ^ "TVA board approves construction of nuclear plant". The Tennessean. 08-18-11. Retrieved August 18, 2011. 
  3. ^ "TVA cuts contractors at Alabama Bellefonte nuclear site". Reuters. Mar 16, 2012. 
  4. ^ http://edocket.access.gpo.gov/2009/E9-19045.htm
  5. ^ http://www.nrc.gov/reading-rm/doc-collections/news/2010/10-012.html
  6. ^ Tennessee Valley Authority Application for a Combined Licence
  7. ^ TVA plan for Ala. nuclear plant drops to 1 reactor
  8. ^ [1]
  9. ^ "TVA board approves construction of nuclear plant". The Tennessean. 08-18-11. Retrieved August 18, 2011. 
  10. ^ http://www.tva.com/power/nuclear/pdf/wb2_performance_summary_dec_2012.pdf
  11. ^ Sonal Patel (June 20, 2013). "TVA Indefinitely Delays Bellefonte Nuclear Project". Retrieved 19 July 2013. 
  12. ^ Brian Lawson (June 12, 2013). "TVA slowing work, cutting jobs at Bellefonte Nuclear plant, project's future being assessed". Retrieved 19 July 2013. 
  13. ^ Flessner, Dave (30 October 2013). "Critics Blast Plan for Private Financing of TVA's Bellefonte Nuclear Plant". Chattanooga Times Free Press (Tennessee). Retrieved 31 October 2013. 
  14. ^ Power Reactor Information System of the IAEA: „Nuclear Power Reactor Details - BELLEFONTE-1“
  15. ^ Power Reactor Information System of the IAEA: „Nuclear Power Reactor Details - BELLEFONTE-2“
  16. ^ Power Reactor Information System of the IAEA: „Nuclear Power Reactor Details - BELLEFONTE-3“
  17. ^ Power Reactor Information System of the IAEA: „Nuclear Power Reactor Details - BELLEFONTE-4“

External links[edit]